Backward pass

Use forward and backward pass to determine project duration and critical path

Check out http://www.engineer4free.com for more free engineering tutorials and math lessons! Project Management Tutorial: Use forward and backward pass to de...
Education video by Youtube Channel


Backward Pass is the calculation of late finish dates and late start dates for the uncompleted portions of all network activities. Determined by working backwards through the network logic from the projects end date. The end date may be calculated in a forward pass or set by the customer or sponsor.