Determine the Early Start (ES) and Early Finish (EF) of activities in a PDM network diagram

Check out http://www.engineer4free.com for more free engineering tutorials and math lessons! Project Management Tutorial: Determine the ES and EF of activiti...
Education video by Youtube Channel


Early Finish Date or EF used in the critical path method. Early Finish Date is the earliest possible point in time on which the uncompleted portions of an activity (or the project) can finish based on the network logic and any schedule constraints. Early finish dates can change as the project progresses and changes are made to the project plan.